ECG sheds 530 MW

    0
    1472
    Changing of underground cabels

    The Electricity Company of Ghana (ECG) is shedding a total of 530 megawatts of power today [Tuesday].

    This follows the Ghana Grid Company’s (GRIDCo) request to ECG.

    A statement from the ECG said the action is due to “insufficient power generation.”

    Below is the full statement:

    PEAK LOAD RELIEF REQUEST FROM GRIDCo

    Date: 24/11/15 ____________________________ ECG is to undertake 530MW load relief between 18:00hrs and 06:00hrs due to insufficient power generation,the regions should therefore shed load as follows: Accra… 220MW

    Group A is coming ON Group B is going OFF Group C is going 24hrs

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here